Wloclawek project at the finish
The end of assembly works of the desulphurization installation at MPEC Włocławek are closer and closer. We are currently finishing the application of technological elements, including compressed air systems, aeration and process water systems.
Works related to the insulation of the filter, ducts, penthouse, etc. are at the end. At the end of the month, electrical and automation installations as well as technological systems and process sensor are to be completed.
Spring will be a test for the entire implementation team, because in the second half of April we will start commissioning. If all goes according to plan, the plant will be put into operation in summer.
We keep our fingers crossed!